Southeast window has been straightened
Progress of sheathing preparation and Buleskin weather barrier
2 Maple trees have been cut down; stumps will be removed.
View from the northwest
Foundation tie in at northeast coner
Foundation at new addition; remaining foundation to tie into new east wall of Cummings to be done.
North end of new East Wall foundation with sleeves for electrical conduit; new timber sill and double pressure treated subsill.
8. New East Foundation wall interior view
Basement with new East Wall foundation in place
New concrete encasement of south chimney piers
Concrete encasement at north chimney piers
Basement view toward access opening in East Wall foundation; flowable fill will rise up to bottom of opening.
Wood braces at granite capstones along west wall
Wood braces at granite capstones along west wall
Concrete infill at section of west foundation wall under Cummings front door to replace loose stones previously in this location.
Detail of top of new East Wall foundation with top of concrete tight to underside of double 2x8 pressure treated subsills
View of stone repointing at south foundation wall
View of stone repointing at west foundation wall; flowable fill will rise to 3 feet below floor framing above.
View of stone repointing at west foundation wall
View of stone repointing at north foundation wall.
View of hearth opening at north hearth
View looking up into north firebox.
Rafter reinforcement at Attic
LVL scabbed onto rafter to transfer load directly to exterior wall below rather than to the outrigger timber beyond the exterior face of the building.
Metal clip angle anchoring LVL to Attic floor assembly
New 2x6 collar ties at each rafter
View of Attic looking north with collar ties; height allows stepping over each tie.
View of Attic looking south
View of south chimney to be repointed.
View of north chimney to be repointed.
View of hearth opening at south fireplace to receive new framing and new bluestone hearth
Brick infill at south fireplace